Newton Ferrers Solar farm

In cooperation with an experienced project development company from Germany and Ireland the team of ENERGISTO gained planning consent for a 20MW solar park in autumn 2014. Another vital project milestone has been the securing of necessary private and public wayleaves for building a more than 8km long cable route. Planning process for grid connection and project sale have been successfully accomplished in January 2015. ENERGISTO supports also during construction phase and commissioning.

19.82 MW
Anlagengröße
Operation
Status

Projektdetails

Cornwall, UK
Region
2014—2015
Zeitraum
Ground Mounted
Anlagenart
approx. 28.7 ha
Anlagenfläche
approx. 20.3 Mio. kWh/a
»Neue Energie«
approx. 6,100
Haushalte
approx. 11,600 t/a
CO₂

Team

Stefan Albrecht
Project Engineering
Clément Delhoume
Project Engineering (grid connection)
Marc Iori
Investor Relations, Project Communication
Thilo von Haas
Investor Relations, Project Sale
Christoph Prenosil
2D/3D Project Visualisation, Project Support (LVIA)

for the local community

  • A payment for community benefits has been secured via a “section 106 agreement”

for the environment

  • A special wild flower seed mix will be sown for increasing the biodiversity
  • The deer fencing around the solar installation will have a 15cm gap at the bottom for small manmals to roam freely
  • Sheep will be grazing between the rows of panels to keep the fields in agricultural use

 

In cooperation with Solar Renewable Projects ltd. we act in the areas of Project Planning / Management and Engineering.